Çumra Sugar 2018 Revision Period Piping and Welding Works

  • Project Contractor : Konya Şeker - ABH
  • Project Year : 2018
  • Project City : Çumra / Konya

Our work items completed in the scope of our 2018 Revision Period Piping and Welding Works project, which we undertook and completed the turnkey project at Çumra Şeker Integrated Facilities are as follows;

  • Reclamation of Lime Stone-Coke Coal Entry Shielding Plates
  • Trigeneration Unit Feed Water Line Piping
  • Wastewater Treatment Plant
  • Lime Milk Line Piping
  • Renewal of Pkf Sherbet Exit Lines
  • Renovation of Pkf Canal Cleaning Lines
  • Renewal of Pkf Drip Plate Channel Pipes
  • B-Green Line Renewal
  • Renewal of Afine Syrup Line
  • Withdrawal of Juicy Sorbet Line
  • Renewing of the Great Edge Band Drip Plate
  • Line Out of Water Treatment Line to Decanter Clean Water Tank
  • Vacuum Boiler Coating Work
  • Maya Tank Coating Work
  • Renewal of Dust Lime Line
  • Welding, Piping etc. Mechanical Work Labor


All of these materials, pipes, fittings, sheet metal, etc. were supplied by OMC. This project, we undertake, has been delivered to our Employer during the campaign stance of the sugar factory that we have promised to Konya Şeker.

In addition to the above mentioned works, labor services were received from the contractor company. Our company has done only the labor service (machine equipment installation, piping, welding works, etc.), at the end of the work for all of these work as the as built projects are prepared isometric and delivered to the employer.

In addition, before the tender, our company received a qualification certificate before the tender by Konya Şeker Technical Office Directorate related to the construction of the work.