Botaş Modernization of Jetty, Ballast and ICF Pipelines and Installation of New Pipelines to the Tank Area

  • Employer:  Botaş
  • Year: 2024-2026
  • Location: Ceyhan / Adana

Project Title

Modernization of Jetty, Ballast and ICF Pipelines and Installation of New Pipelines to the Tank Area

Project Description

This project covers the modernization of existing pipelines in the jetty and land areas, as well as the installation of new lines extending to the tank area. It is executed under a comprehensive EPC model, encompassing infrastructure, mechanical assembly, electrical installations, and automation systems.

Main Scope of Work

  • Dismantling and installation of pipelines in various diameters at the jetty and land zones

  • Procurement and installation of mechanical equipment including valves, actuators, and fittings

  • Manufacturing and installation of a new buffer tank in the ballast area

  • Supply, installation, and integration of instrumentation and automation systems

  • Installation of electrical panels, power supply systems, cable trays, and earthing integration

  • Implementation of lighting and fire-fighting systems

  • Execution of cathodic protection systems

  • Functional testing and commissioning of all systems

Project Type

EPC (Engineering – Procurement – Construction)

Disciplines

Civil Works, Mechanical, Electrical, Automation, Infrastructure

Project Status

Ongoing