Oltu Natural Gas Pipe Line Project is completed.

Oltu Natural Gas Pipe Line Project is completed.

06/10/2017

Gas was taken through the Şahdeniz Natural Gas Pipeline through hot-tap operation. In two years period; 59.000 metre pipe line, two pig stations  (pig shooter and pig holder) and one line valve station were completed in the project.

Completed mechanical works; pipeline welding, nondestructive testing, pipe insulations, hydrostatic testing and caliper testing.

Completed construction works; Excavation, badding, filling works, special passes, construction of stations

Completed cathodic processes; Power transmission line to shooter, cathodic protection of line